Constructions near I 71 exit 50
Roadnow AI Agent Live Update
click anywhere on map to find more Constructions
Click for Real Time Traffic
Current Constructions
- MAPGRE-35-0.08 westbound. A bridge and pavement rehabilitation project on U.S. 35, between the Montgomery County line and the bridge over Grange Hall Road. U.S. 35 West traffic will be reduced to one, 12-foot lane for 90 days (through mid-September). U.S. 35 East will be maintained in two, 12-foot lanes.
GRE-35-0.08 westbound. A bridge and pavement rehabilitation project on U.S. 35, between the Montgomery County line and the bridge over Grange Hall Road. U.S. 35 West traffic will be reduced to one, 12-foot lane for 90 days (through mid-September). U.S. 35 East will be maintained in two, 12-foot lanes.
Start Time: 2025-06-17T15:15:00.000-04:00
End Time: 2026-10-01T07:00:00.000-04:00
map local traffic - MAPRoadwork on Stubbs Mill Rd / County Hwy-35 from I-71 N to Shawhan Rd / Stubbs Mills Rd.
Roadwork on Stubbs Mill Rd / County Hwy-35 from I-71 N to Shawhan Rd / Stubbs Mills Rd.
Start Time: 2025-05-22T07:42:30.000-04:00
End Time: 2025-06-21T08:18:07.671-04:00
map local traffic - MAPRoadwork on Stubbs Mills Rd from Trovillo Rd to I-71 N.
Roadwork on Stubbs Mills Rd from Trovillo Rd to I-71 N.
Start Time: 2025-05-22T08:43:00.000-04:00
End Time: 2025-06-21T08:18:07.671-04:00
map local traffic - MAPGRE-72-7.71 northbound. A bridge replacement on S.R. 72 that carries over Caesar Creek in the village of Jamestown. Through most construction, S.R. 72 will be closed, and motorists will be detoured via U.S. 35 and Old US 35. All work is scheduled to be completed in the fall of 2025.
GRE-72-7.71 northbound. A bridge replacement on S.R. 72 that carries over Caesar Creek in the village of Jamestown. Through most construction, S.R. 72 will be closed, and motorists will be detoured via U.S. 35 and Old US 35. All work is scheduled to be completed in the fall of 2025.
Start Time: 2025-06-02T09:47:30.000-04:00
End Time: 2025-10-01T00:59:00.000-04:00
map local traffic - MAPS.R. 72 over I-71. eastbound. Rehab bridges by repairing the backwall; replacing deck and painting structural steel (S.R. 72 over I-71). Work will be done on Orchard Grove Road over I-71 at a later date for approximately two weeks.
S.R. 72 over I-71. eastbound. Rehab bridges by repairing the backwall; replacing deck and painting structural steel (S.R. 72 over I-71). Work will be done on Orchard Grove Road over I-71 at a later date for approximately two weeks.
Start Time: 2025-04-14T11:33:00.000-04:00
End Time: 2026-07-01T00:59:00.000-04:00