Constructions near Junction at E Victoria Rd

click anywhere on map to find more Constructions

 
 

Current Constructions
  • MAP
    NO LANES BLOCKED . As part of the I-85 interstate widening project, between mile points 77 and 98, expect traffic shifts and reduced lane widths within the project limits through August 2021.
    NO LANES BLOCKED . As part of the I-85 interstate widening project, between mile points 77 and 98, expect traffic shifts and reduced lane widths within the project limits through August 2021.
    Start Time: 2018-01-01T00:00:00.000-05:00
    End Time: 2024-08-31T23:59:59.000-04:00
    maplocal traffic
  • MAP
    1 RIGHT LANE CLOSED . SC 290 / I-85 Intersection will be reconfigured to become a diverging diamond intersection (DDI). Constr. will consist of 6 stages, long term outer lane closures (both dir) on the bridge, and temp lane closures throughout the project at night.
    1 RIGHT LANE CLOSED . SC 290 / I-85 Intersection will be reconfigured to become a diverging diamond intersection (DDI). Constr. will consist of 6 stages, long term outer lane closures (both dir) on the bridge, and temp lane closures throughout the project at night.
    Start Time: 2022-06-15T00:00:00.000-04:00
    End Time: 2024-06-30T23:59:59.000-04:00